Build phases as per documentation

 Phase 01 - Frame triangulation

Started 15/10/2004
Aborted 20/3/2005 (cluster plates, strut lengths)
Completed 16/4/2005

 Phase 02 - Axle strut assembly

Started 15/10/2004
Completed 6/5/2005

 Phase 03 - Main gear mounting / axle drag struts

Started 7/4/2005
Completed 7/5/2005

 Phase 04 - Main gear shock struts

Started 15/10/2004
Aborted 16/10/2004 (need vee block)
Restarted 22/10/2004 (struts cut to length)
Completed 17/5/2005 (drilled)

 Phase 05 - Nose block installation

Started & completed 29/3/2005

 Phase 06 - Engine mount

Started 6/11/2004
Aborted 18/3/2005 (drilling tolerances)
Restarted 20/4/2005
Completed 23/4/2005

 Phase 07 - Fuel tank mount

Started 18/10/2004
Aborted 18/3/2005 (drilling tolerances)
Restarted 22/3/2005
Completed 28/3/2005
Partial re-build 26 & 27/4/2005

 Phase 08 - Rudder pedals and linkages

Started 30/3/2005

 Phase 09 - Mounting the seat

Started 4/6/2005
Completed 18/6/2005

 Phase 10 - Control stick, tail boom and tail section

Started 16/4/2005 (tailboom drilled and attached)
Tailwheel installed 14/5/2005
Control stick installed 18/6/2005
Control stick shortened 18/7/2005
Tail installation started 7/8/2005
Tail offset-mount started 13/12/2005
Finished tail offset 22/12/2005

 Phase 11 - Rotor head cheek plates

Started (drilling templates) 23/6/2005
CAD finalised 6/2/2006
Cheek plates cut 7/2/2006

 Phase 12 - Rudder cable installation

 Phase 13 - Seat belt and shock plate installation

Started 7/5/2005
Machining complete 8/5/2005
Seat belt installed 16/8/2005

 Phase 14 - Engine mounting and fuel tank installation

Started 21/6/2005
Engine mounted 4/7/2005
Mount refactored 8/7/2005
Fuel pump mounted 14/7/2005
Exhaust mounting & ball joint kits ordered 5/8/2005
Exhaust mounted 11/8/2005
Throttle mounting started 14/10/2005
Carburettors, intake silencer & air filter installed 20/10/2005
Intake silencer brackets fabricated 24/10/2005
Engine running 27/11/2005

 Phase 15 - Hang test, rotor control rods, pitch spring

 Phase 16 - Throttle assembly

Quadrant & cabling ordered 3/10/2005
Throttle installation started 14/10/2005