Phase 01 - Frame triangulation
Started 15/10/2004
Aborted 20/3/2005 (cluster plates, strut lengths)
Completed 16/4/2005
Phase 02 - Axle strut assembly
Started 15/10/2004
Completed 6/5/2005
Phase 04 - Main gear shock struts
Started 15/10/2004
Aborted 16/10/2004 (need vee block)
Restarted 22/10/2004 (struts cut to length)
Completed 17/5/2005 (drilled)
Phase 05 - Nose block installation
Started & completed 29/3/2005
Started 6/11/2004
Aborted 18/3/2005 (drilling tolerances)
Restarted 20/4/2005
Completed 23/4/2005
Started 18/10/2004
Aborted 18/3/2005 (drilling tolerances)
Restarted 22/3/2005
Completed 28/3/2005
Partial re-build 26 & 27/4/2005
Phase 08 - Rudder pedals and linkages
Started 30/3/2005
Started 4/6/2005
Completed 18/6/2005
Phase 10 - Control stick, tail boom and tail section
Started 16/4/2005 (tailboom drilled and attached)
Tailwheel installed 14/5/2005
Control stick installed 18/6/2005
Control stick shortened 18/7/2005
Tail installation started 7/8/2005
Tail offset-mount started 13/12/2005
Finished tail offset 22/12/2005
Phase 11 - Rotor head cheek plates
Started (drilling templates) 23/6/2005 CAD finalised 6/2/2006 Cheek plates cut 7/2/2006
Phase 12 - Rudder cable installation
Phase 13 - Seat belt and shock plate installation
Started 7/5/2005
Machining complete 8/5/2005
Seat belt installed 16/8/2005
Phase 14 - Engine mounting and fuel tank installation
Started 21/6/2005
Engine mounted 4/7/2005
Mount refactored 8/7/2005
Fuel pump mounted 14/7/2005
Exhaust mounting & ball joint kits ordered 5/8/2005
Exhaust mounted 11/8/2005
Throttle mounting started 14/10/2005
Carburettors, intake silencer & air filter installed 20/10/2005
Intake silencer brackets fabricated 24/10/2005
Engine running 27/11/2005
Phase 15 - Hang test, rotor control rods, pitch spring
Phase 16 - Throttle assembly
Quadrant & cabling ordered 3/10/2005
Throttle installation started 14/10/2005